Project Update
Throughout November we have updated new kerbs, kerb ramps and installed exposed concrete paths at the Western side of the front car park.
The existing Asphalt surface has also been removed, and preparation works for the new Asphalt surface is underway.
This first stage of work is currently on track be complete by the end of December 2025.
Stage 2 Works are expected from early January 2026 to mid-February 2026.
To see more information regarding the current and planned road and carpark closures - view here
Project Summary
The National Capital Authority (NCA) is commencing a project in the Old Parliament House precinct. Works will include:
Every effort will be made to minimise disruptions during this period; however, some temporary road closures and bus detours will be required. Access to any nearby driveways will be maintained.
Delivery of this package of works will improve the condition of the road infrastructure surrounding OPH, extending their life and safety.
CB Excavations has been appointed (following a competitive procurement process) to deliver the works.
Project Background
The NCA own and manage a large portfolio of civil infrastructure including roads, car parks, paths and stormwater systems.
In 2027 the Museum of Australian Democracy (MoAD) will host events to celebrate the main Old Parliament House (OPH) building turning 100-years old.
The NCA has worked in collaboration with MoAD to identify areas for improvement prior to 2027.
The project timeline is designed to have all works completed in advance of the 2027 celebrations.