Major upgrades are planned for the Blackall Street Intersection on Kings Avenue to facilitate the opening of the John Gorton Campus Car Park later this year. Roadworks are scheduled to commence from Monday 26 August 2024 and will include:
Due to the extensive services relocation works and upgrades required, the works have been programmed to take place simultaneously across three workfaces to minimise long-term disruption. Where possible works will be managed outside of peak usage times to reduce the impact on road users.
The durations and timings outlined below are weather permitting.
Impacts | Duration | Peak/Off peak |
---|---|---|
No entry and exit to Blackall Street from Kings Avenue east-bound (traffic travelling north towards the bridge) | 26 August 2024 – December 2024 | All times, peak and off peak hours |
Left turn closed from Kings Avenue east-bound onto King Edward Terrace | Approx. one month from 26 August 2024 | Off peak |
Kings Avenue west-bound will reduce to one lane at the Blackall Street intersection | Approx. three months from 26 August 2024 | Off peak |
All pedestrian access will be open on Kings Avenue and Blackall Street with some disruptions and detours at times | 26 August 2024 – December 2024 | All times, peak and off peak hours |
*Peak hours: weekdays 7:00 am to 10:00 am and 3:30 pm to 6:30 pm. Off peak hours: weekdays 10:00 am to 3:30 pm and 6:30 pm to 7:00am, 24 hours on weekends and public holidays.
The Department of Finance will continue to issue regular email updates to communicate traffic changes and road user impacts throughout the works.